Submittals, RFIs and change orders on low-voltage jobs
The paperwork that keeps a low-voltage job buildable and paid for: preparing and checking submittals (product data, shop drawings, test reports, certificates, closeout records), acting on review actions, writing requests for information that get useful answers, and recognizing changes so extra work is authorized in writing before it's done. Published procedures (UFGS 01 33 00, FAR 52.236-21 and 52.243-4, and the City of Los Angeles project delivery manual) are used as examples; your contract sets the actual rules and who may authorize changes.
- Level
- Intermediate
- Length
- About 55 minutes
- Contents
- 3 lessons · final exam
- Status
- Published · updated 24 Nov 2026
Skills you'll practise
- Explain what common submittal types contain and why the reviewer's action is needed before material is ordered
- Check a submittal against the specification and clearly identify any deviation before it is sent
- Act correctly on approved, approved-as-noted and revise-and-resubmit actions
- Write an RFI that cites the documents, asks one clear question and says when the answer is needed
- Recognize when a request or an RFI answer is a change and get written direction before doing the extra work
Course outline
- 1.Submittals: what goes in and what comes backLesson · 19 min
- 2.Requests for information that get answersLesson · 17 min
- 3.Change orders and extra workLesson · 19 min
- 4.Submittals, RFIs and change orders on low-voltage jobs: knowledge checkKnowledge check · 18 questions
- 5.Six more drops, and a note that doesn't match the specScenario
- 6.Final exam10 questions · passing it completes the course, so people who already know the material can test out
Sources it draws on
The lessons and questions are written from these references, so learners can go back to the original.
- Unified Facilities Guide Specifications UFGS-01 33 00, Submittal Procedures (August 2026): submittal descriptions SD-01 to SD-11, contractor QC review and stamp, review action codes, resubmittals, approval doesn't relieve the contractor (US federal example)
- Unified Facilities Guide Specifications UFGS-27 10 00, Building Telecommunications Cabling System (May 2025): three-part section; submittal list with 'G' items; T1 to T6 telecommunications drawings; RCDD-approved drawings to TIA-606; record documentation; two Category 6A cables to each WAP outlet per TIA TSB-162 (US federal example)
- FAR 52.236-21, Specifications and Drawings for Construction (Feb 1997): drawings and specifications of like effect; specifications govern where they differ; discrepancies submitted for a written determination; shop drawings defined; variations described in writing; approval doesn't relieve the contractor (US federal contract clause, example)
- FAR 52.243-4, Changes (June 2007): written change orders; other written or oral orders treated as changes only with written notice of date, circumstances and source; equitable adjustment in writing; 20-day and 30-day limits (US federal contract clause, example)
- City of Los Angeles Bureau of Engineering, Project Delivery Manual 16.2: Request for Information (RFI) procedure (clarification of plans, specifications or contract requirements; sequential numbering; not a substitute for a shop drawing submittal; not used to change the design; a change needs a change order)
- City of Los Angeles Bureau of Engineering, Project Delivery Manual 20.1: Change orders, introduction (a change order documents required changes to plans, specifications or contract documents; categories; lump-sum, emergency not-to-exceed and time-and-materials change orders)
- City of Los Angeles Bureau of Engineering, Project Delivery Manual 20.2: Initiating change orders (three categories: changed or unforeseen conditions, errors and omissions, changes in scope; review RFIs, submittals and correspondence; rough order of magnitude estimate and schedule impact; change order log)
- General low-voltage project practice (starter content; needs subject review)
See it with your own jobs and topics
Tell us about your team and we'll walk you through setup, from choosing jobs to your first skills check.